A3 - Integration, dissemination and exploitation

A1 - Programme Management
A2 - Quality Assurance
A3 - Integration, dissemination and exploitation

(A3) Integration, dissemination and exploitation – Table 5
This workpackage with integrate results to produce a final report and provide the main dissemination and communication functions for the project. In addition, this workpackage will arrange a consortium agreement to cover IPR (assisted by the EC Intellectual Property Right Helpdesk (http://www.cordis.lu/ipr-helpdesk) Table 5. Summary Description of Integration, Dissemination and Exploitation Workpackage.
Workpackage Title: Integration, dissemination and exploitation WP nr: A3
Starting date: month 1 Duration: 36 months Total Effort
(MM):
15
Partners involved R & D Task/Activity of Partner Effort (MM):
KUSS A3.2, A3.4, A3.7, A3.8
D-A3.2, D-A3.8/R
15
Objectives
This workpackage governs the integration, dissemination and exploitation of scientific and technical output from IMMORTAL with the following objectives:
Integration
  • Synthesis of project results into a final report summary.
Dissemination
  • Operate dissemination and communication mechanisms to include (i) website; (ii) press releases; (iii) operating links with networks, URP and related projects, and (iv) relevant bulletins in EC journals and magazines.
Exploitation
  • Preparation (and revision) of exploitation plan to include collaboration agreement (e.g., IPR).


Description of work / tasks

Integration
Task A3.2: Synthesise final report (month 30-36).
Dissemination
Task A3.4: Dissemination mechanism(s) (month 1-36).
Task A3.5: Final project seminar (month 33-36)*
Exploitation
Task A3.7: Consortium collaboration agreement (month 4).
Task A3.8: Exploitation plan (month 1-36).
Deliverables
D-A3.2: Final report summary.
D-A3.8: Exploitation plan.
Milestones (and criteria)
Month 4: Completion of collaboration agreement (PRC approval)
Month 12: Completion of exploitation plan, D-A3.8 (EMC approval).
Month 20: Completion of revised exploitation plan from midterm assessment, D-A3.8R (EMC approval).
Month 36: Completion of final summary report, D-A3.2 (EC approval).
Interrelation with other workpackages
This workpackage relates to all research and policy workpackages by providing a central function for integration, dissemination and exploitation.